Net metering: 10-working-day approvals, no notarization, credit rollover

Under the ERC's amended net-metering rules (Resolution No. 15, Series of 2025) and a 2026 joint circular, distribution utilities must process a complete application within 10 working days, or it may be deemed approved.

The agreement no longer has to be notarized, and electronic signatures are accepted. LGUs must issue electrical permits within 3 working days and the CFEI within 7.

The rules also add multi-site and aggregate net metering, rollover of unused credits, transfer of credits when a property is sold, and optional REC meters. No separate barangay permit is needed, though city or municipal permits may still apply.

What it means for you: getting bill credits after installation should take less time and fewer documents. When you get a quote, check that the timeline and paperwork list match these rules.