Net metering with Meralco, step by step (2026 rules)

Net metering lets you earn a peso credit on your bill for solar power you send to the grid. Here are the steps with Meralco.

Updated November 2026

How it works

Net metering is an arrangement under the Renewable Energy Act (RA 9513). Your home uses its own solar power first, and eligible power you export earns a peso credit on your bill (Meralco).

Exports are credited at the monthly blended generation cost, not the full retail rate, so the credit changes from month to month. Power you use yourself is usually worth more than power you export.

The programme is for systems of up to 100 kW per qualified customer. Final approval depends on your system and the local network.

The six stages

  • 1. Application
  • 2. Evaluation
  • 3. Inspection
  • 4. Completion
  • 5. Energization and commissioning
  • 6. Transmittal

At commissioning Meralco checks that the system disconnects within 2 seconds of a grid outage and reconnects after 10 minutes.

Documents Meralco lists

  • Application form, documentary checklist and annex.
  • Authorization and ID, if a representative applies for you.
  • Distribution Impact Study (required) and Distribution Asset Study (when required).
  • Service-entrance inspection.
  • Local electrical permit and Certificate of Final Electrical Inspection (CFEI).
  • Signed Net Metering Agreement and Fixed-Asset Boundary Document.
  • A notarized affidavit and waiver if you decline the optional REC meter.
  • Applicable payments. For homes, the assessed meter cost difference must not exceed ₱3,000 under the referenced ERC advisory.

Transformer limits

  • 10 or 15 kVA transformer: 7 kW.
  • 25 kVA: 10 kW.
  • 50 kVA: 19 kW.
  • 100 kVA: 38 kW.

How much solar can connect depends on the transformer that serves your home. Meralco gives these examples:

What changed in 2026

  • Utilities must process complete applications within 10 working days, or they may be deemed approved.
  • The agreement no longer needs notarization, and electronic signatures are accepted.
  • LGUs must issue electrical permits within 3 working days and CFEIs within 7.
  • Unused credits roll over, and credits can transfer when a property is sold.
  • Multi-site and aggregate net metering are added, and REC meters are optional.
  • No separate barangay permit is needed, though city or municipal permits may still apply.

Under the ERC's amended net-metering rules (Resolution No. 15, Series of 2025) and a 2026 joint circular, as reported in July 2026:

How long it takes

Meralco gives no fixed completion date. Timing depends on permits, studies, inspection and the other steps. Ask your installer for a written timeline and a list of the papers they will handle.